TIMELINE AND IMPACT
- Start date:
- Demolition: September 14, 2026
- Construction: October 2026
- Completion date: Winter 2027
- Closures: Demo zones will be caution-taped off. The restroom, pavilion, and basketball court will be open for as long as possible; for a few days, they will need to be closed due to heavy equipment in the area, concrete pours, etc. Once the restroom demo and renovation begins, it will be closed for a couple of months.
- Phase 1: Closes September 14, 2026
- Phase 2: 1-2 weeks after Phase 1
- Phase 3: 1-2 weeks after Phase 2
Closure Phase Map:

BUDGET
- Project Budget: $700,000.00 (increased from $560,000 in September 2026)
- Funding Source: Parks Capital Improvement Program, Capital Improvement Projects 1/2 c sales tax
- Contractor: TBD
SCOPE OF WORK
- New playground and pour-in-place (PIP) rubber safety surfacing
- Trail replacement
- Improved lighting
- Bathroom renovations (ADA)
- Entrance sign addition
- Fitness court
PUBLIC COMMENTS