TIMELINE AND IMPACT
- Start date: June 2025
- Project completed August 2025
- Temporary closure of the road during construction
BUDGET
- Project Budget: $22,803.55
- Project Cost: $20,803.55
- Funding Source: Parks Capital Improvement Program 1/2 cent sales tax
- Contractor: Higgins Asphalt
SCOPE OF WORK
- Mill and overlay access road to Hough Park Lake
PUBLIC COMMENTS