TIMELINE AND IMPACT
- Construction began December 2025
- Anticipated completion: February 2026
- Temporary closure of restrooms during construction
BUDGET
- Projected Cost: $75,000.00
- Funding Source: Parks Capital Improvement Program 1/2 cent sales tax
- Contractor: Martin Metal, JC Parks staff
SCOPE OF WORK
- Two family restrooms with changing tables
- HVAC for multi-season use
- Exterior lighting
- Epoxy flooring
- Water fountain with bottle filler
- Complete exterior renovation