TIMELINE
- Construction began October 2024
- Project completed February 2025
- Temporary closure of restrooms during construction
BUDGET
- Project Budget: $75,000.00
- Project Cost: $43,569.89
- Funding Sources: Parks Capital Improvement Program 1/2 cent sales tax
- Contractor: JC Parks staff
SCOPE OF WORK
- Two family restrooms with changing tables
- HVAC for multi-season use
- Exterior lighting
- Water fountain with bottle filler
- Complete exterior renovation