TIMELINE AND IMPACT
- Site setup and grading began September 2024
- Project completed June 2024
- Temporary closure of basketball court during construction
BUDGET
- Project Budget: $68,000.00
- Project Cost: $58,009.29
- Funding Source: Parks Capital Improvement Program 1/2 cent sales tax
- Contractor: Stockman Construction
SCOPE OF WORK
- Replace basketball court
- Install new goals
PUBLIC COMMENTS