East Miller Park Pavilion

TIMELINE AND IMPACT

  • Site setup and grading began September 2024
  • Project completed June 2025
  • No anticipated closures

BUDGET

  • Project Budget: $170,000.00
  • Project Cost: $151,783.74
  • Funding Source: Parks Capital Improvement Program 1/2 cent sales tax
  • Contractor: Athco

SCOPE OF WORK

  • Construction of 24′ x 48′ pavilion
    • Steelworx Split-top Gable Shelter
    • Concrete slab beneath shelter
    • Install charcoal grills
  •  