McKay Park ADA Dock and Trail

TIMELINE 

  • Design and planning began November 2024
  • Project completed June 2025
  • Temporary closure of northwest section of trail during construction

BUDGET:

  • ADA Dock Project Budget: $30,000.00; Trail Extension Project Budget: $92,200.00
  • ADA Dock Project Cost: $36,734.09; Trail Extension Project Cost: $92,200.00
  • Funding Sources: MDC Outdoor Infrastructure Grant $60,574; Parks Capital Improvement Program 1/2 cent sales tax
  • Contractors: Denny’s Dock Service – dock and installation; Bartlett & West – ADA design services; Rhad Baker – trail extension

SCOPE OF WORK

  • Dock and installation
  • ADA design services
  • Trial extension
  • Misc: rock, equipment, etc.