TIMELINE
- Design and planning began November 2024
- Project completed June 2025
- Temporary closure of northwest section of trail during construction
BUDGET:
- ADA Dock Project Budget: $30,000.00; Trail Extension Project Budget: $92,200.00
- ADA Dock Project Cost: $36,734.09; Trail Extension Project Cost: $92,200.00
- Funding Sources: MDC Outdoor Infrastructure Grant $60,574; Parks Capital Improvement Program 1/2 cent sales tax
- Contractors: Denny’s Dock Service – dock and installation; Bartlett & West – ADA design services; Rhad Baker – trail extension
SCOPE OF WORK
- Dock and installation
- ADA design services
- Trial extension
- Misc: rock, equipment, etc.
PUBLIC COMMENTS