TIMELINE AND IMPACT
- Start date: February 2025
- Project completed September 2025
- Temporary closure of the restroom during the restroom renovation portion of the project.
BUDGET
- Project Budget: $113,298.00
- Project Cost: $125,531.94
- Funding Source: Parks Capital Improvement Program 1/2 cent sales tax
- Contractor: Athco – shade structure; Martin Metal – restrooms; Centech – HVAC; Consolidated Electrical – electrical
SCOPE OF WORK
- Complete interior and exterior renovation
- New metal exterior finishes
- Upgraded electrical and plumbing
- ADA restrooms
- Epoxy floors
- New interior finishes
- Three-bay sink and stainless steel counter tops
- Improved security and lighting
- Four cantilever style shade structures, 2 (16′ x 24′) and 2 12′ x 12′