TIMELINE AND IMPACT
- Start date: mid-October 2025
- Project Completion: April 2026
- Riverside Pavilion will be closed during construction
BUDGET
- Projected Cost: $560,000.00
- Funding Source: City Capital Improvement 1/2 cent Sales Tax H; Parks Capital Improvement Program 1/2 cent sales tax
- Contractor: Drinkard Construction – renovations; Mid Mo Epoxy – epoxy floors; The Architects Alliance – design work
SCOPE OF WORK
- New exterior finishes
- Stained ceiling
- New siding and doors
- ADA restroom and kitchen renovation
- Upgraded HVAC
- Upgraded MEP (mechanical, electrical and plumbing)
PUBLIC COMMENTS